Newquay Growth Area: Project Programme
The Newquay Strategic Route (NRS) Phase 2 and 3 Design and Construction Current Programme* is shown below.
Date | Stage |
---|---|
February 2018 |
Project start |
May 2018 |
Approval for funding and inclusion in Capital Programme |
October 2018 |
Appointment of Project Management Team |
August 2020 |
Appointment of Contractor for pre-construction phase |
April 2021 |
DoC Construction of Trevenson Road Link |
September 2021 |
Appointment of contractor for Design and Build |
October 2021 |
Start of design |
August 2022 |
Start of construction |
Winter 2024 |
Construction completion/road opening |
* This is an indicative programme. Some milestones may change in order to best deliver the NSR alongside other local developments. The milestones shown on this web page will be kept up to date on a regular basis.
Please follow the links to see:
The Newquay Strategic Route (NRS) Phase 2 and 3 Design and Construction Current Programme* is shown below.
Date | Stage |
---|---|
February 2018 |
Project start |
May 2018 |
Approval for funding and inclusion in Capital Programme |
October 2018 |
Appointment of Project Management Team |
August 2020 |
Appointment of Contractor for pre-construction phase |
April 2021 |
DoC Construction of Trevenson Road Link |
September 2021 |
Appointment of contractor for Design and Build |
October 2021 |
Start of design |
August 2022 |
Start of construction |
Winter 2024 |
Construction completion/road opening |
* This is an indicative programme. Some milestones may change in order to best deliver the NSR alongside other local developments. The milestones shown on this web page will be kept up to date on a regular basis.