Newquay Growth Area: Project Programme

The Newquay Strategic Route (NRS) Phase 2 and 3 Design and Construction Current Programme* is shown below.

DateStage

February 2018

Project start

May 2018

Approval for funding and inclusion in Capital Programme

October 2018

Appointment of Project Management Team

August 2020

Appointment of Contractor for pre-construction phase

April 2021

DoC Construction of Trevenson Road Link

September 2021

Appointment of contractor for Design and Build

October 2021

Start of design

August 2022

Start of construction

Winter 2024

Construction completion/road opening

Continue reading

* This is an indicative programme. Some milestones may change in order to best deliver the NSR alongside other local developments.  The milestones shown on this web page will be kept up to date on a regular basis.